AFC Fylde Contract Update June 2016

AFC Fylde Contract Update
AFC Update Photo 07.06.16 900x600
Bradley’s Sports Bar – Warden Construction built the shell of the new Bradley’s Sports Bar, which officially opened on the 4th June 2016 and is already proving to be a success. The stylish Sport’s Bar includes a huge 12′ x 7′ video wall; 24 63″ TVs; and zonal sound system.

West Stand and signage – The frames and AFC Fylde badges on the side elevations of the West Stand are in place and the ‘AFC Fylde’ LED signage on the pitch side looks fantastic. First fix of the plumbing and electrical work has also begun.

Work is continuing on the ceilings surrounding the main entrance with an opening for the showcase spiral staircase.

On the football side, work has started on tiling the officials changing area and shower trays have gone in.

Ground work around the stadium is expected to be complete within the month and the pathways around the site are currently being tarmacked.

Progress on the pitch – Following the seeding and the installation of sprinklers, and recent spells of sunshine and showers, the grass is starting to come through and the pitch is already looking fantastic.

Overall the site is progressing well.