AFC Fylde Contract Update April 2016

AFC Fylde Contract Update April 2016

Great progress being made for the AFC Fylde stadium contract.

Currently the pitch is being prepared and flattened ready for the drainage works. One of the main jobs this week has been lifting the huge air conditioning units up onto the roof.

The steel work and precast terracing on the South Stand is now complete.  In addition, the terracing work and the canopy of the East Stand has been completed. Cladding has also now started to the rear of the East Stand whilst handrails are currently going up on the South Stand.

Over on the West Stand, the blockwork is now complete and the plastering work has now commenced. The glazing to the pitch side of the West Stand is well underway and the striking black cladding that wraps around the entire stand is all but complete.

Brick and block work and mechanical and electrical installation is ongoing throughout the project and is progressing well.